The table below contains what ZP and I discussed regarding the launch plan. We tried to fit that into the existing timeline with tasks we'll need to complete below that. The numbered steps represent deployments/environment changes/config changes for any of the services. The bullets are general action items and tasks. The horizontal lines separate tasks that can happen after the numbered step above them from tasks that must happen before the numbered step below them.
Step | Date | CMS | API | eGalaxy | Chase | Convio |
---|---|---|---|---|---|---|
1 | June 19 | ecomm | ecomm | staging | sandbox | staging |
2 | June 29 | ecomm | ecomm | production | sandbox | staging |
3 | July 6 | production (0%) | production | production | production | production |
4 | July 10 | production (10%) | production | production | production | production |