Generate MSProject Schedule from YAML
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
#!/usr/bin/ruby | |
%w( yaml pp win32ole ).each { |dep| require dep } | |
class WIN32OLE | |
def self.get_project | |
begin | |
connect('MSProject.Application') | |
rescue WIN32OLERuntimeError => e | |
new('MSProject.Application') | |
end | |
end | |
end | |
class MicrosoftProject | |
attr_accessor :doc_file | |
def initialize(the_doc) | |
@doc_file = the_doc | |
@app = WIN32OLE::get_project | |
@app.Visible = true | |
@doc = @app.FileOpen(@doc_file) | |
@proj = @app.ActiveProject | |
@task_IDs = [] | |
end | |
def add_new_task(args) | |
task_name = args[:task_name] | |
durn = args[:durn] | |
nesting = args[:nesting] + 1 | |
tsk = @proj.Tasks.Add(Name: task_name) | |
tsk.Duration = durn if durn | |
tsk.Text1 = nesting | |
unless @task_IDs.size == 0 || @task_IDs[-1][1] != nesting | |
tsk.Predecessors = @task_IDs[-1][0] | |
end | |
tsk.OutlineIndent while tsk.OutlineLevel < nesting | |
tsk.OutlineOutdent while tsk.OutlineLevel > nesting | |
@task_IDs << [tsk.ID, nesting] | |
end | |
def generate_schedule_from_YAML(obj, nesting=0) | |
counter = 0 | |
obj.each do | task, rest | | |
counter += 1 | |
if rest.is_a? Hash | |
add_new_task( :task_name => task, | |
:nesting => nesting) | |
generate_schedule_from_YAML(rest, nesting+1) | |
else | |
add_new_task( :task_name => task, | |
:durn => rest, | |
:nesting => nesting) | |
end | |
end | |
end | |
end | |
def main(obj) | |
filename = 'F:\IM Methodology\Other Files\Newman PCN Remediation Schedule.mpp' | |
pj = MicrosoftProject.new(filename) | |
pj.generate_schedule_from_YAML(obj) | |
end | |
def test(o, nesting=0) | |
spaces = %q{ } | |
o.each do |task, rest| | |
if rest.is_a? Hash | |
puts spaces * nesting + task | |
test(rest, nesting+1) | |
else | |
puts [spaces * nesting + task, rest].join("|") | |
end | |
end | |
1 | |
end | |
if __FILE__ == $0 | |
obj = YAML::load(DATA) | |
test(obj) == 1 && main(obj) | |
end | |
__END__ | |
--- | |
<<Project Name>>: | |
Initiation: | |
Assessment Workshop: | |
MRA Completed: 0.0d | |
Risk Assessment Completed: 0.0d | |
OCM Assessment Completed: 0.0d | |
Commercial Assessment Completed: 1.0d | |
Documents Assessment Completed: 0.0d | |
Charter Developed: 0.0d | |
Charter Release for Review: 0.0d | |
Charter updated from feedback: 0.0d | |
Charter Approved: 0.0d | |
StageGate 0 Checklist Completed: 0.0d | |
Initiation Completed: 0.0d | |
Approval to proceed to Selection Phase Received: 0.0d | |
Selection: | |
Phase start: 0.0d | |
Program Management: 1.0d | |
Project Management: 1.0d | |
Project Phase Startup: | |
Engage Project Team: 1.0d | |
Create/Review Selection Phase Schedule and Financial Mode: 1.0d | |
Engage Business and IM: 1.0d | |
Review Lessons Learnt register and Similar Projects Learnings: 1.0d | |
Create Deliverables Register: 1.0d | |
Create Deliverables / Signoff matrix: 1.0d | |
High Level Business Requirements Documented: | |
Develop High Level Business Requirements: 1.0d | |
Create/update ARIS Business Process Models: 1.0d | |
Create/Update Business Requirements in Requisite Pro: 1.0d | |
Document High Level Business Requirements Spec (PGO40): 1.0d | |
High Level Solution Designed: | |
Validate SOW with EAO for Selection Phase: 1.0d | |
Create/Update Current State Architecture Models (Baseline - TOGAF B,C,D): 1.0d | |
Create/Update Future State Architecture Models (Target - TOGAF B,C,D): 1.0d | |
Perform Gap Analysis between Current and Future Architectures (TOGAF E): 1.0d | |
Assess Solution Options and Recommend Solutions: 1.0d | |
Prepare Architecture Feasability (PGO04): 1.0d | |
Approval of Architecture Feasability (TOGAF G): 1.0d | |
Update SOW with EAO for Definition Phase: 1.0d | |
Business Req & Solution Design Completed: 0.0d | |
MRA Review: 0.25d | |
STRA Completion: 1.0d | |
Project Plans Strategies Schedules Developed: | |
Project Execution Plan: | |
Develop Project Execution Plan : 1.0d | |
Change Management Strategy: | |
Develop Change Management Strategy : 1.0d | |
High Level Resource Plan: | |
Develop High Level Resource Plan : 1.0d | |
Project Schedule: | |
Develop High Level Project Schedule for Full Project : 1.0d | |
Build Detailed Project Schedule for Definition Phase : 1.0d | |
Project Financial Model: | |
Update Financial Model : 1.0d | |
High Level Quality Plan: | |
Develop High Level Quality Plan : 1.0d | |
Approval for Definition Phase: | |
Plans and Schedule Approved: | |
Review key project Documents : 3.0d | |
Approve all Documents: 1.0d | |
Plans and Schedule Approved: 0.0d | |
PEP Approved: 0.0d | |
Prepare Stagegate 1 Checklist: 1.0d | |
Complete Stakeholder Presentation: 1.0d | |
Stagegate 1: | |
Stagegate 1 Checklist Completed : 1.0d | |
Approval to proceed to Definition Phase Received: 0.0d | |
Submit to P3O : 1.0d | |
Definition: | |
Phase Start: 0.0d | |
Program Management: 1.0d | |
Project Management: 1.0d | |
Project Phase Startup: | |
Engage Project Team: 1.0d | |
Review Lessons Learnt register: 1.0d | |
Update Deliverables Register: 1.0d | |
Update Deliverables / Signoff matrix: 1.0d | |
Detailed Business Requirements : | |
Develop Detailed Business Requirements: 1.0d | |
Update ARIS Business Process Models: 1.0d | |
Update Business Requirements in Requisite Pro: 1.0d | |
Document Detailed Business Requirements : 1.0d | |
Detailed Business Requirements Spec Approved: 0.0d | |
Solution Design Finalised: | |
Functional Detailed Design Documented: | |
Develop Detailed Functional Design: 1.0d | |
Architecture Finalised: | |
Validate SOW with EAO: 1.0d | |
Validate Solutions against Functional Design (TOGAF B,C,D,E): 1.0d | |
Prioritise Work Packages (TOGAF F): 1.0d | |
Prepare Solution Architecture: 1.0d | |
Solution Architecture Approved (TOGAF G): 0.0d | |
Technical Detailed Design (If Infrastructure Project): | |
Develop Technical Detailed Design : 1.0d | |
Assessment Workshop: | |
MRA Review Completed: 1.0d | |
STRA Review Completed: 1.0d | |
IMTRA Completed: 1.0d | |
Risk & Contingency Completed: 1.0d | |
Detailed Project Execution Plans and Schedule: | |
Detailed Change Management Strategy: | |
Finalise Change Management Plans : 1.0d | |
Communications Plan: | |
Develop Communications Plan : 1.0d | |
Test Plan: | |
Develop Test Plan : 1.0d | |
Training Plan: | |
Develop Training Plan : 1.0d | |
Implementation Planning: | |
Develop Implementation Plan : 1.0d | |
Handover & Support Planning: | |
Develop Knowledge Transfer Training Plan: 1.0d | |
Develop Handover and Support Plan : 1.0d | |
Detailed Risk Assessment: | |
Perform Detailed Risk Assessment: 1.0d | |
Update Risk Register: 1.0d | |
Detailed Project Schedule for Full Project: | |
Develop Detailed Project Schedule for Full Project : 1.0d | |
Detailed Resource Plan: | |
Develop Detailed Resource Plan : 1.0d | |
Detailed Project Financial Model: | |
Develop Detailed Project Financial Model : 1.0d | |
Detailed Quality Plan: | |
Develop Detailed Quality Plan : 1.0d | |
Detailed Project Execution Plan: | |
Develop Detailed Project Execution Plan : 1.0d | |
Detailed Business Case: | |
Develop Detailed Business Case : 1.0d | |
Benefits Realisation Plan: | |
Develop Benefits Realisation Plan : 1.0d | |
Approval for Execution Phase: | |
Plans and Schedule Approved: | |
Review key project Documents : 3.0d | |
Approve all Documents: 1.0d | |
Plans and Schedule Approved: 0.0d | |
PEP Approved: 0.0d | |
Prepare Stagegate 1 Checklist: 1.0d | |
Complete Stakeholder Presentation: 1.0d | |
Initiate Supply process: 1.0d | |
Stagegate 1: | |
Stagegate 1 Checklist Completed : 1.0d | |
Approval to proceed to Execution Phase Received: 0.0d | |
Execution: | |
Phase Start: 1.0d | |
Project Management: 1.0d | |
Project Startup: | |
Engage Project Team: 1.0d | |
Perform Project Team Kickoff: 1.0d | |
Perform Supply process for Purchases and Maintenance: 1.0d | |
Project Plans and Schedule Reviewed: | |
Revise Project Schedule : 1.0d | |
Revise project Financial Model : 1.0d | |
Review Resource Plan : 1.0d | |
Review Change Management Strategy : 1.0d | |
Review Communications Plan : 1.0d | |
Review Implementation Plan : 1.0d | |
Review Handover Plan : 1.0d | |
Review Quality Plan : 1.0d | |
Revise Risk and Issues: 1.0d | |
Review Project Execution Plan : 1.0d | |
Obtain Business Approval for changes: 1.0d | |
Conduct Stakeholder kickoff: 1.0d | |
Solution Developed: | |
Build Configure and Unit Test: | |
Build Solution: 1.0d | |
Build Unit Test Plan : 1.0d | |
Conduct Unit Testing: 1.0d | |
Solution Complete: 0.0d | |
Finalise Solution Architecture with actual Architecture: 1.0d | |
Finalise Technical Detailed Design with actual Config: 1.0d | |
Update CIO Springboard with solution details: 1.0d | |
System and Integration Testing: | |
Build System Test Plans : 1.0d | |
Build Integration Test Plans : 1.0d | |
Conduct System Testing: 1.0d | |
Conduct Integration Testing: 1.0d | |
Prepare Test Report : 1.0d | |
User Acceptance: | |
Build UAT Plans : 1.0d | |
Conduct UAT Testing: 1.0d | |
Prepare UAT Test Report : 1.0d | |
Obtain UAT signoff: 1.0d | |
Finalise Implementation Plan : 1.0d | |
Finalise Handover Plan : 1.0d | |
Training Delivered: | |
Finalise Training Plan : 1.0d | |
Develop Training Content: 1.0d | |
Deliver Training: 1.0d | |
Manage and Deliver Knowledge Transfer Training: 1.0d | |
Assess Training Results: 1.0d | |
Organisational Changes Implemented: | |
Implement Communications Plan : 1.0d | |
Implement Organisational Changes: 1.0d | |
Approval for Go-Live: | |
Prepare Stagegate 3 Presentation Pack : 1.0d | |
Conduct Program Office Review of and other Docs: 1.0d | |
Plans and Schedule Approved: 0.0d | |
PEP Approved: 0.0d | |
As Built Review Completed: 2.0d | |
AAG Approved the "As Built Review": 2.0d | |
Prepare Stagegate 3 Checklist: 1.0d | |
Complete Stakeholder Presentation: 1.0d | |
Initiate Supply process: 1.0d | |
Stagegate 3: | |
Stagegate 3 Checklist Completed : 1.0d | |
Approval to proceed to Operations Phase Received: 0.0d | |
Operation: | |
Program Management: 1.0d | |
Project Management: 1.0d | |
Hand-Over Benefits Realisation Plan: 1.0d | |
Solution Implemented: | |
Prepare for Implementation: 1.0d | |
Conduct Implementation: 1.0d | |
Solution Live: 0.0d | |
Approval for Project Close-Out: | |
Project Close-Out Tasks: | |
Handover to Business and Support: 1.0d | |
Perform Project Review / Lessons Learnt Workshop: 1.0d | |
Prepare Project Close-Out Report : 1.0d | |
Prepare Close-Out documents : 1.0d | |
Archive Project Records: 1.0d | |
Finalise & Carry out Close out of Financials: 1.0d | |
Run Lessons Learnt Workshop: 1.0d | |
Update Lessons Learnt Database: 1.0d | |
Demobilise team: 1.0d | |
Vendor Evaluation Carried out: 1.0d | |
Syndicate Docs with IM and Key Business Stakeholders: 1.0d | |
Close Out Approved: 0.0d | |
Prepare Stagegate 4 Checklist: 1.0d | |
Complete Stakeholder Presentation: 1.0d | |
Initiate Coomercial process: 1.0d | |
Stagegate 4: | |
Stagegate 4 Checklist Completed : 1.0d | |
Approval to Close Down Project Received: 0.0d | |
Post Go-Live Support: | |
Post Go-Live Support: 1.0d | |
... |