displayMode: compact
---
gantt
title Roadmap
dateFormat YYYY-MM-DD
axisFormat %b '%y
tickInterval 3month
2023 : 2023-11-01, 2023-12-31
2024 : 2024-01-01, 1y
2025 : 2025-01-01, 1y
2026 : 2026-01-01, 1y
2027 : 2027-01-01, 1y
2028 : 2028-01-01, 1y
PI 23-4 : pi23-4, 2023-11-01, 3M
PI 24-1 : pi24-1, 2024-02-01, 3M
PI 24-2 : pi24-2, 2024-05-01, 3M
PI 24-3 : pi24-3, 2024-08-01, 3M
PI 24-4 : pi24-4, 2024-11-01, 3M
PI 25-1 : pi25-1, 2025-02-01, 3M
PI 25-2 : pi25-2, 2025-05-01, 3M
PI 25-3 : pi25-3, 2025-08-01, 3M
PI 25-4 : pi25-4, 2025-11-01, 3M
PI 26-1 : pi26-1, 2026-02-01, 3M
PI 26-2 : pi26-2, 2026-05-01, 3M
PI 26-3 : pi26-3, 2026-08-01, 3M
PI 26-4 : pi26-4, 2026-11-01, 3M
PI 27-1 : pi27-1, 2027-02-01, 3M
PI 27-2 : pi27-2, 2027-05-01, 3M
PI 27-3 : pi27-3, 2027-08-01, 3M
PI 27-4 : pi27-4, 2027-11-01, 3M
Active :active, cw, 2024-02-01, 3M
N/A :crit, np, after cw, 3M
pre-GW Work : pre-gw, after np, 12M
On-prem Artifacts : onprem, after pre-gw, 12M
Cloud Artifacts : cloud, after onprem, 2029-08-01
Roadmap Start : milestone, rm, 2024-02-01, 0m
Gateway : milestone, gw, after pre-gw, 0m
Production-ready : milestone, ready, after pre-gw, 12M
gantt
title Roadmap
dateFormat YYYY-MM-DD
axisFormat %b '%y
tickInterval 3month
- : 2023-11-01, 2029-08-01
Active :active, cw, 2024-02-01, 3M
N/A :crit, np, after cw, 3M
pre-GW Work : pre-gw, after np, 12M
On-prem Artifacts : onprem, after pre-gw, 12M
Cloud Artifacts : cloud, after onprem, 2029-08-01
Roadmap Start : milestone, rm, 2024-02-01, 0m
GW : milestone, gw, after pre-gw, 0m
Ready : milestone, ready, after pre-gw, 12M
JAB Live : milestone, jablive, after ready, 12M
VIT Live : milestone, vitlive, after vit2, 0m
section Development
Not planned :done, dnp, after vit2, 2y
section Build
Build Farm :done, buildfarm, after rm, 18M
Build Orch :active, buildorch, after rm, 3M
Win Nodes : buildnodes, after np, 3M
Lin Nodes : buildnodes, after np, 3M
BNS SCA :active, bnssca, after np, 3M
BNS LS : bnsls, after np, 3M
Artifact Storage :done, arti, after rm, 18M
Cntr Registry :active, creg, after rm, 3M
Arti In : artiin, after np, 3M
Arti Out : artiout, after np, 3M
VCS :done, vcs, after np, 3M
VCS Req : vcsreq, after np, 3M
section Physical Lab Integration Test
Not planned :done, after gw, 2y
section Virtual Integration Test
Req & Design :done, vit1, after np, 3M
Develop and Test :done, vit2, after buildfarm onprem, 12M