Sprint Date Items
1 15-21 Dec Stylesheet, C9, Documentation plan, accessibility checklist, code review process. QA process, Finalize templates.
2 22 Dec-6 Jan 20 modules (Design, development, documentation, QA, accessibility)
3 7-24 Jan 18 modules (Design, development, documentation, QA, accessibility)
4 25-31 Jan Final QA, Finetunes, consolidation, compliance with submission requirements.
- Every module should be simple.
- Following steps should be taken for every module to mark it done a. Requirement (Purpose, fields, design structure) b. Design and development c. QA d. Documentation
- Total 38 modules
-
Required skills
Project management, Development, design, documentation, QA
-
Roles
Val - Mentor, frontman Umer - Illustrations to be designed by Umer as per specifications given by Usman. Usman - PM and QA Ahmed - Frontend tech lead Hammad - Frontend developer Abdullah - Frontend developer Umair - Code review, documentation, any technical help needed, mentor.
- Prepare a list of accessibility
- While working on a module do design, development, QA, documentation, accessibility.
- QA also includes code review, and label checks.
- Documentation to be done after QA.
- Officially work on team financial share.
- Umair to finish his work module by module. 1 hour call every other day during sprint 2 and 3.
- Usman to setup WBS on Monday.com